| Province | Subbasin | % |
|---|---|---|
| Columbia Cascade | Entiat | 20.00% |
| Methow | 40.00% | |
| Wenatchee | 40.00% |
| Previous: | Next: |
|---|---|
| n/a |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Survey and hydraulic modeling completed on select projects | B: 114. UC Survey and hydraulic modeling Contract - 2010-58 | 05/31/2014 | 05/27/2014 | |
| Produce Designs for Small Restoration Projects | C: 175. UC Small Project Design - 2010-57 | 05/31/2014 | 05/27/2014 | |
| Groundwater pump tests complete | D: 148. Install Piezometer Wells and Conduct Groundwater Pump Tests 2010-37 | 05/31/2014 | 05/27/2014 | |
| lwd procure and hauling | E: 98. Large Wood Procurement - 2010-59 | 05/31/2014 | 05/27/2014 | |
| Wetland Delineations and Rare Plant Surveys completed | F: 165. Wetland Delineation and Rare Plant Surveys - 2010-44 | 05/31/2014 | 05/27/2014 | |
| UCHRP Public Outreach Campaign | G: 99. UCHRP Public Relations - 2010-42 | 05/31/2014 | 05/27/2014 | |
| River User Risk Assessments | H: 174. UC River User Safety Plans - 2011-61 | 05/31/2014 | 05/27/2014 | |
| Submit reports documenting all contacts made | I: 191. Outreach Supporting Habitat Restoration Activities (Methow) 2009-22 | 05/31/2014 | 05/27/2014 | |
| Landowner Outreach completed | J: 99. CCD Landowner Outreach & Coordination - 2010-60 | 05/31/2014 | 05/27/2014 | |
| Produce Native Plant restoration and Soil Bio-Engineering Design, Materials, and Installation | K: 47. UC Native Plant Restoration and Soil Bio-Engineering - 2010-62 | 05/31/2014 | 05/27/2014 | |
| Funding Package - Submit draft to COTR | L: 119. Manage personnel, property and subcontracts for overall UCHRP | 05/31/2014 | 05/27/2014 | |
| Vegetation Maintenance | N: 197. Methow Subbasin Vegetation Maintenance - 2010-4 | 05/31/2014 | 05/27/2014 | |
| Post Implementation Monitoring | O: 115. UC Post Implementation Field Monitoring 2012-85 | 05/31/2014 | 05/27/2014 | |
| Engineering Support Services | P: 122. On-call Engineering Support Services 2009-17 | 05/31/2014 | 05/27/2014 | |
| Sheet pile testing | Q: 186. UC Sheet Pile Geo-Tech 2012-83 | 05/31/2014 | 05/27/2014 | |
| Maintain, Repair, Install and/or Remove | R: 186. UC Construction Services 2012-82 | 02/28/2014 | 02/28/2014 | |
| Vegetation Maintenance | S: 197. NEW CCR29202 Vegetation Maintenance Wenatchee & Entiat 2012-84 | 05/31/2014 | ||
| Conduct land pre-acquisition activities to determine suitability of land purchases | T: 172. NEW CCR29202 Lands Acquisition 2012-104 | 05/31/2014 | ||
| LWD procured and hauled | U: 29. Large Wood Procurement - 2010-59 | 05/31/2014 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
| Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 06/01/2012 | ||||||
| B | 114 | UC Survey and hydraulic modeling Contract - 2010-58 | 06/01/2012 | ||||||
| C | 175 | UC Small Project Design - 2010-57 | 06/01/2012 | ||||||
| D | 148 | Install Piezometer Wells and Conduct Groundwater Pump Tests 2010-37 | 06/01/2012 | ||||||
| E | 98 | Large Wood Procurement - 2010-59 | 12/02/2011 | ||||||
| F | 165 | Wetland Delineation and Rare Plant Surveys - 2010-44 | 06/01/2012 | ||||||
| G | 99 | UCHRP Public Relations - 2010-42 | 06/01/2012 | ||||||
| H | 174 | UC River User Safety Plans - 2011-61 | 06/01/2012 | ||||||
| I | 191 | Outreach Supporting Habitat Restoration Activities (Methow) 2009-22 | 06/01/2012 | ||||||
| J | 99 | CCD Landowner Outreach & Coordination - 2010-60 | 06/01/2012 | ||||||
| K | 47 | UC Native Plant Restoration and Soil Bio-Engineering - 2010-62 | 06/01/2012 | ||||||
| L | 119 | Manage personnel, property and subcontracts for overall UCHRP | 03/01/2012 | ||||||
| M | 132 | Report submitted under Coordination contract | 03/01/2012 | ||||||
| N | 197 | Methow Subbasin Vegetation Maintenance - 2010-4 | 03/01/2012 | ||||||
| O | 115 | UC Post Implementation Field Monitoring 2012-85 | 03/01/2012 | ||||||
| P | 122 | On-call Engineering Support Services 2009-17 | 06/01/2012 | ||||||
| Q | 186 | UC Sheet Pile Geo-Tech 2012-83 | 06/01/2012 | ||||||
| R | 186 | UC Construction Services 2012-82 | 06/01/2012 | ||||||
| S | 197 | NEW CCR29202 Vegetation Maintenance Wenatchee & Entiat 2012-84 | 06/01/2012 | ||||||
| T | 172 | NEW CCR29202 Lands Acquisition 2012-104 | 06/01/2012 | ||||||
| U | 29 | Large Wood Procurement - 2010-59 | 06/01/2012 |